Mark Step Complete
From the Planned and pending steps sections on the Details tab of the Plan page, you can mark a selected step complete and record date and status information for the completed step. The step is then moved into the Completed steps section.
-
From the Planned and pending steps sections on the Details tab of the Plan page, select the step you want to mark as “Complete”.
-
Select the drop-down arrow next to Step and select Mark complete. The Mark step complete screen appears.
-
In the Date field, today’s date defaults. If the completion date is different from today’s date, enter the date on which the step was completed.
-
Select Save to save the information and return to the Overdue steps tab.